Section 12.08.060 Digging of surface and base materials.
Surface and subbase materials, other than those specified in Section 12.08.050
shall be removed
by hand or machine in such a manner as to disturb or displace the least possible surface area in
excess of that which must be removed for the item to be installed. The sides of the trenches four or
more vertical feet in depth shall be sloped to an angle equal to or greater than the angle of repose
of
the material being excavated. No undercutting of subgrade shall be permitted. If undercutting
occurs, that section where undercutting took place shall be excavated and repaired in conformity
with Section 12.08.050. (Ord. 155 (part), 1999: prior code § 12.03.060)