Section 12.08.100 Obligation of applicant.
A. An applicant for a permit to excavate any surface
within public right-of-way of the city
shall within fifteen (15) calendar days of issuance of such permit repair and complete the surface of
such excavation. Extension of time may be granted by the public works director or designated agent
upon showing of justifiable cause by the permittee, such extension when granted must be in writing.
B. If inspection of a project while under construction
finds construction methods being
practiced not conforming to Sections 12.08.020 through 12.08.090, a correction notice will be
issued by the public works director or designated agent listing items of procedures not meeting
requirements of the above sections. Three calendar days' action is required of permittee to bring
items listed on correction notice into conformity with the above sections. If corrections listed on
notice are not brought to conformity with the above sections in the specified time period, a stop
work order for the project will be issued. Work on the project shall only resume after a meeting
with the permittee, the public works director and the agent who issued the stop work order. If
project is not brought to conform with the above sections, the public works director or designated
agent shall cause the excavation to be placed in a condition that does not meet the requirements of
the above sections. Costs shall be against the applicant's bond under Section 12.08.010, with legal
action against the applicant's business. (Ord. 155 (part), 1999: prior code § 12.03.100)