Section 16.12.050 Preliminary plat approval period.

    A.    Upon approving or conditionally approving a preliminary plat, the city council shall provide the subdivider with a dated and signed statement of approval. This approval shall be in force for not more than three calendar years or less than one calendar year. At the end of this period the city council may, at the request of the subdivider, extend its approval for a period of not more than one year except that the govering body may extend its approval for a period of more than one year if that approval period is included as a specific condition of a written subdivision improvements agreement between the city council and the subdivider.
    B.    After the preliminary plat is approved, the city council may not impose any additional conditions as a prerequisite to final plat approval, providing said approval is obtained within the original or extended approval period as provided above.

Table 16.12.050
Overview: Preliminary Plat Review Process

    1.    Initial Contact with Director of Community Development. Applicant obtains guidelines, forms, and regulation.
    2.    Pre-Application Conference. Applicant discusses proposal and sketch plan with subdivision administrator. Potential problem areas are identified and regulations are highlighted.
    3.    Submittal of Formal Application. To the director of community development twenty-one (21) work days prior to a regular meeting of the planning board. If the planning board determines that the application is complete, the planning board, at its meeting, shall authorize publication of notice of a public hearing to be held at its next regular meeting. The sixty (60) day review period begins on the date that the planning board determines the application to be complete.
    4.    Notification. Fifteen (15) days prior to public hearing, notice of hearing published and letters mailed to adjacent property owners and subdividers.
    5.    On-Site Investigation and Administrative Review. By director of community development.
    6.    Planning Board. Public hearing conducted and subdivision reviewed and recommendation to city council is provided.
    7.    Approval. City council action to approve, conditionally approve or disapprove plat must be completed within the sixty (60) day time limit and submitted in writing. (Ord. 152 (part), 1999; Ord. 131 (part), 1998: prior code § 16.01.020B-5)